During the last several months, contractors successfully completed the restoration of the seawall, installed underground utilities and poured concrete for walkways and planters at parcels east and west of Chene Park.  The iconic stainless steel RiverWalk railing, benches and waste receptacles are in place at both locations.  Contractors are now installing light poles and security cameras.  At the entrance to Chene Park, the remaining concrete planters are being poured and work on the circular concrete section adjacent to Atwater Street is now underway.

Crews will be back on site at both parcels in the spring for the installation of all final landscaping.